2018 Village Watermain Improvements

This locally funded project will replace approximately 3,300 linear feet of water main on the 400 blocks of Rose, May, and Grace Streets, along with Washington Street from York Road to Marion Street. As part of this project, the Village will also be replacing water service up to the existing b-box, conducting spot curb and gutter repairs, spot sidewalk repairs, and roadway resurfacing. In addition, driveway aprons impacted by the construction will be replaced, parkways will be restored, and other miscellaneous items will be addressed as necessary. The project is expected to start on April 2, 2018 with a final completion date of September 28, 2018. A project information letter is attached.

Download Information Letter No. 1

Update 05/18/18

During the week of May 14th , the contractor worked on water service transfers on May St. The contractor also worked on successfully pressure testing the watermain on Rose St. Currently, the chlorination of watermain on Rose St is underway. Weather permitting during the week of May 21st, the contractor will finish service transfers on May St prior to moving over to Rose St for water service transfers. Tentatively, the week of May 29, the contractor will make final watermain connections at Jefferson St on all three streets (May, Rose and Grace). This will require a water shutdown for at least two separate days and impacted residents will be notified. Spot curb, driveway and sidewalk repairs within the project limits will begin shortly thereafter

Update 05/04/18

During the week of April 30th , the contractor transferred two services for Bridgeway on Washington Street as well as transfer individual home services on Grace St. Watermain on May St also passed the pressure test this week and chlorination is currently underway. During the week of May 7, the contractor is scheduled to complete water services on Grace St and then will likely begin watermain installation on Rose St.

Update 04/20/18

During the week of April 16th , the contractor finished installation of 8-in watermain on Grace St along with some storm sewer manhole reconstruction. During the week of April 23, the contractor is tentatively scheduled to begin watermain installation on May St and/or Rose St, depending on passing the pressure test of the new main on Washington St

Update 04/13/18

During the week of April 9th , the contractor finished installation of 8-in watermain on Washington St. Weather permitting, the contractor will continue to install new watermain down Grace St during the week of April 13 as well as pressure test and chlorinate the watermain on Washington St.