Railroad Ave/Metra Lot Improvements

Railroad Ave/Metra Lot – The contractor is scheduled to mobilize during the week of July 2 with traffic and erosion control scheduled to be installed that week. The work is anticipated to begin during the week of July 9. This project has a substantial completion date of October 30, 2018. The project is designed to be constructed under complete road closures. Railroad Ave will be constructed under complete closures. Traffic will be detoured to Main St during construction.  Access to businesses/residents and emergency vehicles will be maintained. The Metra commuter lot will also be constructed under complete closure. Railroad Ave between York Rd and Center St will be reconstructed with a new Hot-Mix Asphalt pavement, stamped sidewalk, C&G, driveway aprons, planter boxes, benches, striping and landscape restoration. The Metra commuter lot will be reconfigured to allow for PACE bus stop as well as bus layover space.

Information Letter