Church Rd Pump Station Improvements

The Village of Bensenville owns and operates the 1.8 million gallon underground reservoir as well as 500,000-gallon water tower along Church Rd, which is a key facility for the intake and distribution of domestic water throughout the Village. This facility is scheduled to receive electrical and mechanical upgrades as part of this project to replace the original equipment from 1959. The station requires permanent upgrades to effectively operate the facility which will continue to serve the Village for years to come. This locally funded project will begin early May 2020 and will be substantially completed by September 1, 2020. The final completion date is September 30, 2020.

View project information letter

GIS Bensenville Construction Story Maps 

Update 07/09/2020

During the week of July 4, 2020, the contractor has incurred some delays and have not performed any major work.  

Update 06/26/2020

During the week of June 22, 2020, the contractor worked on lead paint removal and remediation. The contractor plans to work on some small miscellaneous items during the week of June 29 ahead of the major work to take place following July 4th. The contractor is still in the process of obtaining final inspection approvals on some of the mechanical and electrical items to be installed in the building.

Update 06/19/2020

During the week of June 15, 2020, the contractor worked on rouging in the electrical cabinets inside the station. The contractor plans to work on some small miscellaneous items during the week of June 22 ahead of the major work to take place following July 4th. The contractor is still in the process of obtaining final inspection approvals on some of the mechanical and electrical items to be installed in the building. 

Update 06/12/2020

During the week of June 8, 2020, there was no work onsite. The contractor is still in the process of obtaining final inspection approvals on some of the mechanical and electrical items to be installed in the building. Should they become available, that work will tentatively commence the week of June 15.

Update 06/05/2020

During the week of June 1, 2020, the contractor finished the exterior electrical work required. The contractor is still in the process of obtaining final inspection approvals on some of the mechanical and electrical items to be installed in the building. Should they become available, that work will commence the week of June 8 or week of June 15.