2021 MFT Street Improvement Project

The project will take place on Red Oak St and Crest Ave east of York Rd, Park St between Jefferson St and Pine Ave as well as Rose St, Marion St and Park St south of Jefferson St. The project was advertised in the IDOT local roads bulletin on Feb 11 and Feb 18. The bid opening took place on Feb 25, 2021. A total of nine bidders submitted their bids for the project. The bids are currently being tabulated for accuracy. Based on as-read bid results but apparent low bidder is Builders Paving, LLC at $975,988.00. Staff is planning to present the contract award for Village Board consideration on Mar 9, 2021. At this time, staff is anticipating the tentative project start date is April 5, 2021, weather permitting.

Update 04/08/2021

During the week of April 5, the sidewalk, C&G and driveway aprons scheduled to be removed and replaced have been marked in the field. Traffic control signs have also been installed throughout the project limits. Weather permitting, during the week of April 12, the concrete sub-contractor is scheduled to be onsite to begin saw cuts, removal and replacement of sidewalk, C&G and aprons.

Update 04/02/2021

The project will take place on Red Oak St and Crest Ave east of York Rd, Park St between Jefferson St and Pine Ave as well as Rose St, Marion St and Park St south of Jefferson St. The project was awarded to Builders Paving LLC on Mar 9, 2021. During the week of March 29, the contractor performed pre-construction videotaping of the site. At this time, the contractor is still finalizing contracts with its subcontractors and hopes to mobilize and possibly start concrete work the week of April 5th, weather permitting.

Update 03/26/2021

The project will take place on Red Oak St and Crest Ave east of York Rd, Park St between Jefferson St and Pine Ave as well as Rose St, Marion St and Park St south of Jefferson St. The project was awarded to Builders Paving LLC on Mar 9, 2021. The pre-construction meeting took place on March 22, 2021. At this time, staff is anticipating the tentative project start date is April 5, 2021, weather permitting.

Update 03/18/2021

The project will take place on Red Oak St and Crest Ave east of York Rd, Park St between Jefferson St and Pine Ave as well as Rose St, Marion St and Park St south of Jefferson St. The project was awarded to Builders Paving LLC on Mar 9, 2021. The pre-construction meeting will take place on March 22, 2021. A more detailed construction schedule will be available at the meeting. At this time, staff is anticipating the tentative project start date is April 5, 2021, weather permitting.

Update 03/11/2021

The project will take place on Red Oak St and Crest Ave east of York Rd, Park St between Jefferson St and Pine Ave as well as Rose St, Marion St and Park St south of Jefferson St. The project was awarded to Builders Paving LLC on on Mar 9, 2021. At this time, staff is anticipating the tentative project start date is April 5, 2021, weather permitting.