2021 Addison Township Resurfacing Program

The Addison Township Highway Department will be performing a heat scarification resurfacing program in the area bound by Third Avenue, Church Road, 2nd Avenue, and IL83 beginning the week of September 20th. Brothers Asphalt Paving, in conjunction with Gallagher Asphalt, will be performing the project. A pre-construction meeting was held this week at the Township Highway Department offices. Traffic Control will be challenging on this project with its vicinity to Johnson School. The project should take three weeks to complete. 

Addison Resurfacing