Update 09/16/2021

Some additional structural repairs were found and completed this week. We are hoping to stay on track for an early October painting of the tank. 

The contractor has erected their sandblasting protection shield and has begun their blasting process. The contractor expects to take one week to blast and prime coat the exterior, one week to blast and prime coat the interior, and one week to put the final coatings on the tank. 