2022 Residential Street Lighting Project

PROJECT SCOPE

This year’s Residential Street Lighting Project consists of installing new streetlights along 1.12 miles of residential streets.  Construction activities include installing 47 new streetlights, electric cable in conduit, underground conduits, lighting controller, helix foundation, and landscape restoration in the right-of-way.

During construction, traffic will be maintained with daily lane closures and flaggers.  The project is expected to be substantially completed by mid-May 2024 with final completion and landscape restoration completed by May 24, 2024.

Project Details

Contract Bid Date: October 31, 2023, 11:00 A.M
Contract Award Date: November 14, 2023
Project Cost: $509,761
Awarded Contractor: Utility Dynamics Corporation
Construction Start Date: January 2024
Construction Completion Date: May 24, 2024
Funding Sources: Community Development Block Grant and Capital Improvements Funds

Project Contact Information

Village of Bensenville Resident Engineer
Brad Hargett, P.E. Brad Hargett, P.E.
Assistant Village Engineer Assistant Village Engineer
Email: bhargett@bensenville.il.us Email: bhargett@bensenville.il.us
Phone: 630-350-3411 Phone: 630-350-3411

Project Documents

Name Link to Document
As-Read Bid Results  View
 

Project Updates

02.16.2024
This week, the contractor Utility Dynamics continued with installation of the underground conduits for the street lighting cables along Franzen Street, Stoneham Street, and Kevin Lane.  Next week, Utility Dynamics will finish the underground conduits with installation along Green Valley Street and Twin Oaks Street.

02.09.2024
The contractor Utility Dynamics continued with installation of the underground conduits for the street lighting cables along Addison Road and Argyle Street. They also commenced installing handholes along Belmont Avenue, Center Street, and Addison Road. Next week Utility Dynamics will continue with the installation of underground conduits along Argyle Street and Green Valley Street.

01.26.2024
This week, the contractor Utility Dynamics began mobilizing to the project site. Preconstruction work has begun with installation of advanced warning signs and project layout. They also initiated construction mid-week with installation of the underground conduits for the street lighting cables along the south side of Belmont Avenue.  Next week, Utility Dynamics will continue with installation of underground conduits along Center Street then Addison Road.