Check back regularly for updates on IL Route 390 / Elgin O’Hare Western Access construction through and around the Village of Bensenville. All work is weather dependent. Drivers should continue to watch for changing traffic patterns, milled surfaces, uneven pavement levels, and traffic shifts. Use caution at all times. Sign up to receive these updates by email or text.
Tollway (4670) – IL 19 (York Rd to Taft Ave) –Update 10/06/17
The contractor is working on widening IL-19 east of York Rd. Two lanes of traffic on the EB IL-19 were re-open on October 4, 2017 between York Rd and Taft Ave. A traffic shift is scheduled for EB IL-19 starting on October 11, 2017. The two EB lanes will be shifted to the right so the contractor can begin working on median improvements. This configuration will last until mid-November. WB traffic will remain in current configuration of two open lanes but will be shifted to the left between South Access Rd and York Rd. The contractor is scheduled to work on pavement widening and median improvements.
Tollway – IL 19 (York Rd to Taft Ave) –Update 10/02/17
4644-The contractor is currently working on wrapping up the staining of IL-83 bridge. They are also working on miscellaneous punch list items. (5975)
4662- The contractor finished pacing of the last segment of the bike path along Frontage Rd and York Rd. They also worked on finishing up the sanitary valve vault work at Supreme Lift station as well as miscellaneous items. (5973)
4670 - The contractor is working on widening IL-19 east of York Rd. Next week, the contractor is scheduled to work on C&G placement, fine grading and pouring mainline pavement in the EB direction. They will also be working on earth excavation, under drains and storm sewers in the westbound direction.
4662- The contractor finished pacing of the last segment of the bike path along Frontage Rd and York Rd. They also worked on finishing up the sanitary valve vault work at Supreme Lift station as well as miscellaneous items. (5973)
4670 - The contractor is working on widening IL-19 east of York Rd. Next week, the contractor is scheduled to work on C&G placement, fine grading and pouring mainline pavement in the EB direction. They will also be working on earth excavation, under drains and storm sewers in the westbound direction.
Tollway (4670) – IL 19 (York Rd to Taft Ave) –Update 09/22/17
During the week of 9-25-17, weather permitting, the contractor is scheduled to work on C&G placement, fine grading and pouring mainline pavement in the EB direction. They will also be working on earth excavation, under drains and storm sewers in the westbound direction
Tollway (4670) – IL 19 (York Rd to Taft Ave) –Update 09/14/17
During the week of 9-18-17, weather permitting, the contractor is scheduled to work on fine grading and pouring mainline pavement in the EB direction. They will also be working on earth excavation and storm sewers in the westbound direction. The motorists are advised to expect long delays and/or seek alternate routes.
EOWA 4644 - Advance Notification - IL Route 83 Traffic Shift
Starting Monday, May 22, 2017 traffic on northbound Illinois Route 83 will shift to the left and the right lane will close between Foster Avenue and EB Frontage Road will be closed. The northbound IL 83 will be reduced to two lanes. This traffic stage will allow for the east side of northbound Illinois Route 83 to be constructed. This traffic shift will remain in place until early June.
Maintenance of Traffic MOT Plan
Project Updated- EOWA (4662)
Starting Monday, May 15, traffic will shift to the right on southbound York Road between Supreme Drive and the South Frontage Road with the right shoulder closed. This traffic stage is the final configuration for contract 4662.
4662 Final Striping
4662 Final Striping
4670 Stage Construction
This project consists of widening of IL-19 from east of York Rd to Taft Ave. Pre-stage construction is scheduled to begin on Thursday April 20, 2017 with installation of temporary traffic signals at IL-19/South Access Rd as well as temporary lighting. Off-peak single lane closures will be utilized while performing the Pre-stage construction work. Stage 1 MOT (drawings attached) is scheduled to be set up on Friday, May 5 with a duration of approximately 12 weeks. In Stage 1 there will be one lane of traffic open in the eastbound direction and two lanes of traffic open in the westbound direction between just east of York Road to just west of Taft Ave.
Construction Update- 4662 Northbound Thomas Drive Detour 03/27/17
Thomas Dr at South Frontage Rd will be closed to northbound traffic from 4-3-17 to 4-10-17 for roadway pavement work. The northbound traffic will be detoured as shown on the attached exhibit.
Construction Update 4644 – 03/27/17
Supreme Dr is scheduled to be open in both northbound and southbound direction starting tomorrow March 28, 2017. A new traffic signal has been installed at North Frontage Rd and Supreme Dr which will go live tomorrow. South Frontage Rd and Supreme Dr is currently controlled by a traffic signal.
Construction Update 4644 – Illinois Route 83 Beam Erection
Contract 4644 is currently scheduled to begin beam erection for the eastbound and westbound Illinois Route 390 bridges over Illinois Route 83 on Sunday, February 26. One left lane in each direction of Illinois Route 83 between Foster Avenue and Mark Street will close at 6 p.m. One left turn lane in each direction of Illinois Route 83 between the eastbound Frontage Road and westbound Thorndale Avenue will also close at this time A second lane in each direction of Illinois Route 83 between Foster Avenue and Mark Street will close at 9 p.m. Full 15 minute intermittent stops will occur in both the northbound and southbound directions between 9 p.m. and 5 a.m. to allow for the beams to be set. All lanes will reopen by 6 a.m. on Monday, February 27. Similar nighttime closures will occur on Monday, February 27 through Thursday, March 2 and Sunday, March 5 through Thursday, March 9.
Traffic Shift Updates for EOWA 4662 / South Frontage Rd-- 10/24/2016
South Frontage Rd: A traffic shift to the new South Frontage Road between York Road and Supreme Drive is currently scheduled for Monday, November 7 at 4 p.m. The intersection of York Road and Thorndale Ave will be removed and the intersection of the South Frontage Road and York Road will be opened. This shift will allow for the IL-390 and I-490 interchange to be constructed. This will be the final configuration for contract 4662 at this location.
MAINTENANCE OF TRAFFIC SCHEMATIC - STAGE 2A
MAINTENANCE OF TRAFFIC SCHEMATIC - STAGE 2A
EOWA 4644 / Supreme Dr - Update
Supreme Dr – Due to unforeseen utility conflicts, the detour will remain in place until the permanent traffic signals are installed at Supreme Dr/Frontage Roads. At this time, the traffic signal installation is anticipated to take place in November 2016. During this time, there are more utilities that need to be installed through this corridor. A definitive time line of construction will be provided once the utility conflicts have been resolved.
Traffic Shift Updates for EOWA 4662 / Thomas Dr Detour-- 10/10/2016
Thomas Dr - The northbound lane of Thomas Drive at Thorndale Ave will close at 7 a.m. on Monday, October 17 and a detour will be posted. This detour will route traffic via Foster Ave and York Road to Thorndale Ave. This closure is necessary because it will allow for the construction of the intersection at Thomas Drive and the South Frontage Road. This detour will last 22 days and will reopen by 4 p.m. on Tuesday, November 8. Thomas Drive Detour Plan_01262016
Sievert Court - A portion of Sievert Court will close at 7 a.m. on Monday, October 18 and a detour will be posted. This detour will route traffic onto a newly constructed road that will connect Thorndale Ave and Sievert Court. This closure is necessary because it will allow for the construction of the intersection at York Road and the S Frontage Road. This detour will last 25 days and will reopen by 7 a.m. on Saturday, November 12. Upon the completion of this detour Sievert Court will no longer connect with York Road but will connect to the S Frontage Road (see attached for the realignment).
Sievert Court - A portion of Sievert Court will close at 7 a.m. on Monday, October 18 and a detour will be posted. This detour will route traffic onto a newly constructed road that will connect Thorndale Ave and Sievert Court. This closure is necessary because it will allow for the construction of the intersection at York Road and the S Frontage Road. This detour will last 25 days and will reopen by 7 a.m. on Saturday, November 12. Upon the completion of this detour Sievert Court will no longer connect with York Road but will connect to the S Frontage Road (see attached for the realignment).
Traffic Shift Updates for Supreme Drive and Thorndale Ave- 09/19/2016
Supreme Drive (4644) : Beginning at 8 am Wednesday, September 22, 2016, Northbound Supreme Drive between the Frontage Roads will be shifted to the right (east). Northbound and southbound traffic 700’ south of the South Frontage Road will be shifted to the outside with one lane open in each direction. The southbound lanes of Supreme Drive between the Frontage Roads will continue to be closed for pavement reconstruction with a posted detour. This traffic shift will allow the contractor to continue pavement reconstruction in these locations. This shift is expected to remain in place until early October 2016.
Thorndale Ave (4662): Beginning at noon on Saturday, September 24, 2016, The westbound and eastbound lanes of Thorndale Ave between Higgins Creek and Supreme Drive will be shifted north onto a newly constructed runaround. Two lanes of traffic will remain open in each direction. This traffic shift will begin at noon on Saturday, September 24 and will last until mid-November. This traffic shift will allow the contractor to perform pavement reconstruction in this location.
Maintenance of Traffic MOT Plan - Stage 3B Supreme Drive
Maintenance of Traffic MOT Plan - Thorndale Avenue, RUNAROUND DETAIL
Thorndale Ave (4662): Beginning at noon on Saturday, September 24, 2016, The westbound and eastbound lanes of Thorndale Ave between Higgins Creek and Supreme Drive will be shifted north onto a newly constructed runaround. Two lanes of traffic will remain open in each direction. This traffic shift will begin at noon on Saturday, September 24 and will last until mid-November. This traffic shift will allow the contractor to perform pavement reconstruction in this location.
Maintenance of Traffic MOT Plan - Stage 3B Supreme Drive
Maintenance of Traffic MOT Plan - Thorndale Avenue, RUNAROUND DETAIL
Frontage Road Traffic Shifts Scheduled To Begin This Month (between I-290 and York Road) - August 19
Traffic shifts are scheduled to begin at the end of August to move traffic onto
a new frontage road system along Thorndale Avenue between I-290 and York Road to allow for the construction of the new Illinois Route 390 Tollway east toward O’Hare International Airport.
As part of the Illinois Route 390 Project, the Illinois Tollway is improving and constructing new local access roads along Thorndale Avenue, including a new system of frontage roads. New frontage roads will accommodate local traffic and will provide existing businesses and residential areas with access to the new Illinois Route 390 Tollway.
Electronic message signs and construction signage will be put in place in advance to alert drivers to dates and times for the scheduled traffic shifts. The traffic shifts are necessary to provide a work zone that safely accommodates the construction of the new roadway. All work is weather dependent...
READ FULL RELEASE
a new frontage road system along Thorndale Avenue between I-290 and York Road to allow for the construction of the new Illinois Route 390 Tollway east toward O’Hare International Airport.
As part of the Illinois Route 390 Project, the Illinois Tollway is improving and constructing new local access roads along Thorndale Avenue, including a new system of frontage roads. New frontage roads will accommodate local traffic and will provide existing businesses and residential areas with access to the new Illinois Route 390 Tollway.
Electronic message signs and construction signage will be put in place in advance to alert drivers to dates and times for the scheduled traffic shifts. The traffic shifts are necessary to provide a work zone that safely accommodates the construction of the new roadway. All work is weather dependent...
READ FULL RELEASE
IL Route 83 (Industrial Dr to Mark St) - July 11, 2016
A traffic shift to the east side of the roadway is scheduled to take place along IL Route 83 due to the ongoing Tollway construction. The northbound shift will begin on Monday July 18, 2016 starting at 9:00 PM IL-83 between Industrial Dr and Mark St will be reduced to two lanes in each direction. The southbound shift will begin on Tuesday July 19, 2016 starting at 9:00 PM. Weather permitting, during the traffic shift, pavement removal, roadway, storm sewer installation and earthwork will occur to accommodate the construction for the future interchange of Illinois Route 83 at Illinois Route 390. This traffic shift will remain in effect for until Oct 1, 2016. During this time, left turn movement onto Bryn Mawr Ave from IL-83 north and south bound will be restricted.
Traffic Shift Update
Traffic Shift Update
IL Route 83 (Industrial Dr to Mark St) - May 3, 2016
A traffic shift to the west side of the roadway is scheduled to take place along IL Route 83 due to the ongoing Tollway construction. On Thursday May 5, 2016 starting at 9:00 PM IL-83 between Bryn Mawr Ave and Mark St will be reduced to two lanes in each direction. Weather permitting, during the traffic shift, pavement removal, watermain, storm sewer installation and earthwork will occur to accommodate the construction for the future interchange of Illinois Route 83 at Illinois Route 390. This traffic shift will remain in effect for until July 22, 2016. During this time, left turn movement onto Bryn Mawr Ave from IL-83 north and south bound will be restricted.
Please see attached plan sheets and detour map
Please see attached plan sheets and detour map
Supreme Dr (south of Thorndale Ave) - April 8, 2016
Supreme Dr south of the Thorndale Ave intersection will go into stage traffic starting Tuesday April 19, 2016 with one lane open in each direction (no left turn lane) due to ongoing Tollway construction project. Weather permitting, reconstruction of Supreme Dr (up to approximately 500 feet south of intersection at Thorndale Ave) and utility relocation work will be performed during this stage. This traffic stage is anticipated to remain in effect until Mid-August 2016.
Please see attached exhibit for detour route
Please see attached exhibit for detour route
Supreme Dr (Thorndale Ave to 700 feet north of Thorndale Ave)- July 11, 2016
Supreme Drive from Thorndale Ave to approximately 700 feet north of Thorndale Ave intersection will be completely shut down to traffic starting at 9:00 AM on Wednesday April 13, 2016 due to ongoing Tollway Construction. Weather permitting, the closure is to remain in effect until approximately Mid-August 2016. During this time, a new intersection with westbound Frontage Rd will be constructed. Traffic will be detoured using Thorndale Ave-York Rd- Supreme Dr.
Please see attached exhibit for detour route.
Please see attached exhibit for detour route.
IL Route 83 (Bryn Mawr Ave to Mark St)- April 05, 2016
A traffic shift is scheduled to take place along IL Route 83 due to the ongoing Tollway construction. On Monday April 18, 2016 starting at 9:00 PM IL-83 between Bryn Mawr Ave and Mark St will be reduced to two lanes in the northbound direction. The southbound traffic will also be reduced to two lanes starting on Tuesday April 19, 2016 at 9:00 PM. Weather permitting, during the traffic shift, box culvert, storm sewer installation and pavement patching will occur to accommodate the construction for the future interchange of Illinois Route 83 at Illinois Route 390. This traffic shift will remain in effect for approximately 5 weeks.
Attached is the plan sheets depicting the traffic